Date
Attendees
- Jocelyne Fiaux (Deactivated)
- Bryan Jones (Deactivated)
- Carmen Nitsche (Deactivated)
- Abhinandan Raghavan (Deactivated)
- Kieran Todd (Deactivated)
Discussion items
Time | Item | Who | Output |
---|---|---|---|
17:00 - 17:30 (30 mins) | >Internal stakeholder package | >All | >Agree framework for internal stakeholder package and responsibilities |
17:30 - 18:00 (30 mins) | >Finish populating assay table: -Gather information for all assays highlighted (based on the required pre-work) -Go through the table to agree information, check for accuracy and address gaps -Definitions less important at this stage | >Richard/All | >Correlate and establish common and uncommon assays used across organisations >Agreed level of assay 'comparability' and 'production process' dependency >Agreement on which data needs to be shared to meet our objectives |